What’s the quickest and slowest deployment in your career?
Minutes? Hours? Days? Months? Years? Let’s hear it!
Don’t settle for months, you’ve got Equinix within minutes. Be the first to test drive Equinix Deploy and use our self-service capabilities acros...
Raf
3 years agoLevel 1
It took about 1.5 years to get a rack delivered to the DC of a competitor who tends to abuse contractors...
I've had a lot of problems with the service provider installing a fibre panel in a rack that was marked "to be destroyed" / the type of rack that was no longer in stock / the electrical connection partly done - then completed 3 months later...
gialyons
3 years agoEquinix Employee
Rafoof, painful. What's the quickest deployment you've ever experienced?
- Raf3 years agoLevel 1
As an ISP; probably the installation of a fibre (FTTB) in less than a week:
- Order validation at D0
- Set up of equipments (CPE) + operator part done at D+3
- intervention of technicians on the customer site on D+5
- Administrative delivery of the order the next day...
=> Very satisfied customer !
With most "big" operators, the usual delay is 4 to 6 weeks minimum.
Related Content
- 4 years ago
Recent Discussions
Featured Places
Discussions
Engage with industry experts, share insights, ask questions, and grow your network.Ideas
We're listening! Submit your ideas to shape the future of Equinix!Groups
Ready to collaborate? Join a Group or upcoming beta program.What's New
Stay ahead with the latest from Equinix. Discover new product announcements, insightful tutorials, and practical use cases.Events
Your Guide to Upcoming Events - Online, Hybrid, and In-Person!